ANALISA PECAH PENYULANG METRO DI UNIT LAYANAN PELANGGAN TANJUNG PANDAN

  • Edoar Achmed Purnama
  • Asmar Asmar
  • Fardhan Arkan

Abstract

In an electric power system has a base voltage and end voltage, where at the end of the network has a decrease in voltage. The standard set for the minimum voltage allowed at the end is 19 kV in accordance with the SPLN. The case study taken is a feeder with the name metro which is one of the feeders who has a below-standard mark of value at the PLN Pandan Tanjung Service Unit.The calculation of the analysis discussed using load flow simulation software by simulating the metro feeder in accordance with the field, then make 3 schemes ideal conditions that can improve the tip stress on the metro feeder.From the simulation results, the best ideal conditions for follow-up repairs can be obtained based on the value of the feeder tip voltage by calculating the cost of the investment based on the length of the feeder being built.

Keywords: End Voltage, new feeder, Length of Feeder and Load Flow simulation Software

Downloads

Download data is not yet available.

References

Referensi Jurnal:

Cahyanto, Dwi Restu. 2007. Studi Perbaikan Kualitas Tegangan dan Rug-Rugi Daya. Skripsi

Kadir, Abdul. 2000. Distribusi dan Utilisasi Tenaga Listrik. Jakarta: Universitas Indonesia

Dadang Iskandar. 2013.Sistem Informasi Gardu Induk dan Gardu Distribusi Berbasis Web, Jurnal Ilmiah, ISSN 2301 – 4156, diakses pada tanggal 8 April 2016.

Belfias. 2017 Analisa Pecah Beban Penyulang Kb5 (Elang) Untuk Perbaikan Tegangan Dan Susut Di Rayon Koba Dengan Menggunakan Etap 12.6. Pangkal Pinang : Universitas Bangka Belitung

Referensi Buku:

SPLN-1-1995. Tegangan- Tegangan Standar

SPLN-72-1987. Spesifikasi Desain Jaringan Tegangan Menengah